ORDNext – The New Concourse E
Chicago, Illinois
Our Aviation Business Unit focuses on the vertical and landside projects that shape the passenger experience and support airport and airline operations. That includes both new and renovated terminals and concourses, consolidated passenger checkpoints, Federal Inspection Stations, parking and rental car facilities, both inbound and outbound baggage handling systems, passenger boarding bridge installation, hangars, cargo and maintenance facilities, support buildings, and central utility plants and building systems.
We work at a variety of different airports across the country, from large hub airports to regional airports, matching the team to each project and program. Our experience ranges from new concourses and terminal modernization to parking structures, utility reconstruction, baggage improvements, central plants and smaller operational projects across an airport campus.
The core challenge is maintaining airport, airline and passenger operations while construction advances. Work must be phased around gates, roadways, security checkpoints, baggage operations, utilities and occupied spaces. Temporary routes and systems must work reliably before the existing condition changes. We are laser focused on protecting the passenger experience.
Airport work also occurs within tightly controlled operating and security environments. Badging, escorted access, vehicle inspections, safety requirements, limited work windows and coordination with airport operations must be built into the production plan.
Clayco pursues aviation work where early contractor involvement can improve the outcome, primarily through construction manager at risk, construction manager/general contractor and progressive design-build delivery. During preconstruction, we validate existing conditions, develop phasing, test constructability, reconcile cost and schedule, and identify long-lead equipment before those issues limit the project.
Our integrated resources add virtual design and construction, building systems expertise, direct procurement, enclosure and concrete capabilities, field operations and independent quality oversight. They help the team coordinate complex systems, evaluate prefabrication and design-assist opportunities, and plan commissioning and operational readiness around phased turnover.
This approach combines open-book decisions, local market participation and disciplined execution in active facilities.
Chicago, Illinois
St. Louis, Missouri
Chicago, Illinois
Idaho Falls, Idaho
Chicago, Illinois
Chicago, Illinois
Chicago, Illinois
Chicago, Illinois
Jacksonville, Florida
Huntsville, Alabama
Chicago, Illinois
Huntsville, Alabama
St. Louis, Missouri
Van Nuys, California
Houston, Texas
Van Nuys, California
Everything in a terminal follows how passengers, baggage and aircraft move through it. The plan must connect those movements while preserving flexibility for future needs.
Passenger flow. Walking distance, vertical circulation and wayfinding among ticketing, security, baggage claim, curbside and parking shape the traveler experience. Those routes must work in the completed building and during construction.
Adaptable space and accessible systems. Clear-span spaces are easier to reconfigure as needs evolve. Baggage, security, technology and building systems also need access, redundancy and isolation points for future maintenance and replacement.
Infrastructure capacity. Terminal growth depends on utilities, central plants, roadways and stormwater systems that passengers may never see. They must support the opening day program and planned expansion.
Phasing from day one. At an operating airport, the design must be buildable in stages. Temporary circulation, gate availability, baggage operations, secure boundaries and utility cutovers are design inputs, not details to solve later.
Gate flexibility. Fleet mixes and airline schedules change faster than buildings do. Building hold rooms large enough to support multiple aircraft type is the most common solution. However, there are other options, including flexible gates like Multiple Aircraft Ramp System (MARS) configurations. MARS gates, where appropriate, can serve one large aircraft or multiple smaller aircraft. O’Hare’s new Concourse D includes 19 of these gates.
Airport sustainability begins with operating performance. Terminals and support facilities run continuously, so the enclosure, mechanical and electrical systems, controls, lighting and metering have a lasting effect.
Energy and resilience. High-performance envelopes, efficient central utilities, heat recovery, modern controls and planned redundancy can reduce energy use and improve reliability. During replacement projects, temporary capacity, cutover planning and commissioning preserve service while new systems come online.
Materials and embodied carbon. Concrete mixes, structural systems, enclosure choices and reuse decisions should be evaluated early, while the team can still compare cost, availability and carbon impact.
Water, stormwater and site systems. Airport campuses contain extensive paved areas and tightly coordinated utilities. Thoughtful civil design can improve resilience and preserve land for future development.
Construction impacts. Waste diversion, material sourcing, equipment emissions and temporary energy use matter. Planning must account for secure access, limited laydown and operating restrictions so commitments remain achievable in the field.
Start with comparable aviation experience, then focus on how the proposed team plans to use it.
Can they protect ongoing operations? Ask for examples of work completed in occupied terminals, secure areas and active airport campuses. The answer should address passenger routing, airline coordination, gate impacts, baggage operations, utility continuity and the specific work windows that controlled production.
Do they bring the right preconstruction discipline? A strong aviation builder should develop progressive estimates, reconcile cost at design milestones, evaluate constructability, build project-specific phasing and convert risks into early decisions.
Do they understand the systems behind the terminal? Baggage, security, communications, controls and central utilities cross traditional trade boundaries. The team should coordinate those interfaces through testing, commissioning and operational readiness.
Can they manage procurement and the local market? Long-lead equipment can control the schedule. The partner should identify risk during design, engage key trades early and pair buying power with strong local participation.
Is the proposed team available? Aviation resumes matter, but so do the people assigned to the work. Evaluate whether the leaders, managers and superintendents have relevant experience and will remain engaged.
How will they collaborate? Airport programs involve many owners, designers, airlines, agencies and facilities staff. Look for clear decisions, open-book cost management and communication that supports daily operational coordination.
Under construction manager at risk, or CMAR, the builder is selected by an airport or air carrier client early in design as a preconstruction advisor and later assumes responsibility for construction, typically under a guaranteed maximum price.
Airports use CMAR because early builder involvement helps resolve the issues that most affect cost, schedule and operations.
Constructability and phasing. Logistics, secure access, passenger routes, utility tie-ins and temporary systems are easier to design around than to work around. The builder can test the sequence early.
Progressive cost certainty. Airport programs often span years and funding cycles. Estimates at defined design milestones identify cost drivers, reconcile scope and support decisions before the guaranteed maximum price.
Early work and procurement. Investigations, enabling work, utilities and long-lead equipment can be packaged ahead of the full construction documents when the contract and funding allow.
Transparency. CMAR’s open-book structure gives public owners visibility into estimates, contingencies, buyout and changes while preserving competition among trade partners.
By treating airport operations as a fixed requirement and designing the construction plan around them.
The work begins with investigations and coordination with airport operations, facilities staff and airlines. That information defines secure boundaries, work hours, gate constraints, utility loads, passenger routes and temporary conditions.
Construction advances through defined phases. Temporary walls, walkways, baggage routes and utility systems are verified before the existing condition changes. Each transition includes contingency planning and stakeholder approval.
Disruptive activities move into controlled work windows. Utility cutovers, crane operations, demolition and work near aircraft may occur at night or during closures. The plan includes setup, testing and restoration within that window.
Construction traffic remains separated from passengers, employees and aircraft. Haul routes, deliveries, laydown, craft parking and access points are planned for each phase.
Turnover is progressive. New spaces and systems are inspected, tested, commissioned and made operational before passengers, airlines or facilities teams depend on them, allowing the airport to remain open as the work advances.